Project Name
Demolition Project SOGEX DESAL 1-6
Project Company
MARAFIQ
Project Duration
- Estimated: 360 days
- Actual: 12 months (365 days)
- Start Date: 01/07/2021
- End Date: 01/07/2022
Project Description
In the city of Yanbu, specifically within the industrial city, the dismantling and removal process of the desalination units at Marafiq Company has been completed, despite the challenges we have overcome by the grace of God, which include heavy loads, high elevations, and transportation operations inside and outside the company. The project was completed without any notable incidents.