Project Name

Dismantling and removal of Yanbu power station

Project Company

SEC

Project Duration
  • Estimated: 60 days
  • Actual: 2 months (60 days)
  • Start Date: 21/01/2024
  • End Date: 21/03/2024
Project Description

In the midst of many challenges related to working at great heights and safely removing flammable materials from the site in high-temperature conditions, the work was completed, which involved dismantling gas turbines and cutting diesel tanks, in a brief period of less than two months. The work was carried out with high precision and professionalism, earning the satisfaction of everyone.