Project Name

Demolition and removal projects in the city of Jeddah (Al-Rawabi neighborhood)

Project Company

Jeddah Company

Project Duration
  • Estimated: 750 days
  • Actual: 19.7 months (602 days)
  • Start Date: 09/06/2022
  • End Date: 01/02/2024
Project Description

Only 6 months after starting the demolition and removal works in the Al-Thaaliba neighborhood, the Metal Collecting Company began demolition and removal works in the Al-Rawabi neighborhood. This increased the project challenges in terms of the large number of equipment and workers involved. However, the company managed to complete the project in parallel with the demolition and removal works in the Al-Thaaliba neighborhood, bringing the total area demolished to over 4 million square meters in a record time of less than two years.